The Challenge
In downtown Calgary, the area around Calgary Tower is one of the city's highest-traffic destinations. The pay station where the island was being constructed sees a constant volume of vehicles moving in and out, and that didn't stop for construction day.
Pittman Concrete had to form, pour, finish, and clean up a commercial concrete island in a single day, all while:
- Working within a tightly constrained physical space
- Managing public safety alongside worker safety in an active, high-traffic environment
- Redirecting live vehicle traffic as needed throughout the day
- Maintaining the pace required to complete the full scope before the site needed to be handed back
There was no margin for delay. The site couldn't be shut down overnight, and the client needed the crossing arms secured and the island fully finished by end of day.
The Approach
Thorough preparation before arriving on site made the one-day completion possible. Pittman Concrete mapped out the sequencing of work, the traffic redirection plan, and the safety protocols in advance, so when the team arrived, there was no time lost figuring out logistics on the fly.
Throughout the day, the team managed active traffic redirection, maintained a safe working perimeter, and executed the form, pour, and broom finish to commercial specification. Site clean-up was completed the same day, leaving the pay station operational and the concrete island ready to do its job.
The Result
The project was completed in a single day in one of downtown Calgary's most active traffic environments. The concrete island is now a permanent fixture, securing the crossing arms and providing clear traffic separation for the pay station.
Pittman Delivered
- Commercial concrete island with broom finish
- Traffic redirection management throughout project duration
- Public and worker safety management on an active site
- Full site clean-up on completion