Silver Springs Condo Site

Project Type: Commercial 
Location: Silver Springs, Calgary ​​​​​​​
Services: Full concrete removal and replacement of footings, walls, and sidewalk ​​​​​​​
​​​​​​​​​​​​​​Timeline: Five-day active construction scope, plus seven-day cure period

  • Pittman Concrete managed a full concrete overhaul at a Silver Springs condominium site.
  • Scope covered demolition, footing installation, wall construction, sidewalk finishing, and fence reinstallation.
  • The complete five-day project was managed by a single contractor from start to finish.

The Project

Pittman Concrete was contracted to complete a full concrete removal and replacement at a condominium site in Calgary’s Silver Springs neighbourhood. The scope covered the removal of an existing fence and the demolition and removal of previous concrete walls, footings, and sidewalk. Once the previous concrete elements were removed, our team installed new footings, walls, and a finished sidewalk. The fence was also reinstalled upon completion.

Before

After

The Scope

This was a complete start-to-finish concrete overhaul. Pittman Concrete managed every phase of the project.

 

Days 1–2

Demolition 

Removal of the existing fence, followed by full demolition and removal of the previous walls, footings, and sidewalk. The site was cleared and prepared for the new installation.

Day 3 

Footing Installation 

New footings were poured and finished to specification, ready to cure before wall installation could proceed.

 

Days 4–5

Wall Installation 

Walls formed and poured two days after the footings, allowing adequate cure time before loading. Walls were left to cure for a full seven days before the project was signed off.

Sidewalk & Finishing 

Sidewalks were poured and broom-finished alongside the wall installation. The top of the wall received a matching broom finish for a clean, consistent look.

Fence Reinstallation 

With the concrete work complete, the fence was reinstalled, leaving a clean, finished site for the condominium residents and management.

The Result

A full concrete overhaul was delivered by Pittman Concrete in five working days, with every phase, including demolition, footings, walls, sidewalk, and fence reinstallation. The condominium site was left with new, properly constructed concrete infrastructure built to last, with minimal disruption to residents throughout the process.

Pittman Delivered

  • Fence removal and reinstallation
  • Full demolition and removal of existing walls, footings, and sidewalk
  • New footing installation poured and finished
  • Formed and poured concrete walls
  • Broom-finished sidewalk and wall tops
  • Full site clean-up on completion